DesignationISO/IEC/IEEE DIS 42703
Stage40.99, DIS approved for FDIS
Planning date, an estimate13 Sep 2027
Published source todayIEEE Std 7003-2024
Dated plan

A twelve-week path to the record

The plan below is the order the standard expects. It is a default, not a promise: a small system can compress it and a large one will extend it. The dates are relative to your start, and the planning date of 13 September 2027 is an estimate for the edition, not a deadline for you.

The page adds the calendar dates for week 1 and week 12. With JavaScript off, the relative labels still work.
WhenClauseWhat is producedOwner
Before the first workshopClause 4.2 inputsBusiness requirements and the necessity record, design documentation, governance packSystem owner
Week 1Clause 4.4Bias requirements, sensitive attribute list, representation test, boundariesProgramme lead
Week 2Clause 4.3 and 5.2Bias profile version 1, values statement, version ruleProfile owner
Week 3 to 4Clause 6.4Stakeholder reference set, types, attributes, protected attributesStakeholder lead
Week 5 to 6Clause 7.4.2.1 and 7.4.2.2Data set record, metadata, proxy analysis, explorationData lead
Week 7Clause 7.4.2.3Data map, imbalance log, retraining linkData lead
Week 8Clause 8.4Two risk inventories, metrics and rationale, signaturesRisk lead
Week 9Clause 8.5Owner acceptance and residual riskSystem owner
Week 10 to 12Clause 9.2Design and output evaluation, nine-item reportEvaluation lead
Week 13Clause 9.3.4.1Monitoring list, recurrence rationale, feedback routeOperations lead
Every iterationClause 9.3.4.3Five-part profile review and new versionsProfile owner
At each triggerClause 1.4Re-entry: new data, new context, update or decommissionProgramme lead

Print this page for the project wall. The paid kit carries the same plan with an editable date, an owner column and a status column per line.

THE ORDER

Why the plan starts at clause 4

Clause 4.1

The profile and the requirements come first because every later step reads them. The stakeholders come before the data because the data map needs a population. The risk assessment comes after both because it takes them as inputs. The evaluation comes last because it tests the design against the requirements, and the monitoring comes after the evaluation because it needs the baseline. A plan that starts with the model will produce tests without a standard.

THE RULES THIS IS BUILT FROM

The rules this is built from

Read from the real rules, not invented. Every clause answer on this site points to the official rule behind it, so you can check any line yourself. The register holds 67 records, 269 evidence lines and 201 common failure lines. The dates come from the ISO record. The substance comes from the published IEEE edition behind the joint project.

61 CLAUSES

One page per clause

The requirement in our words, the evidence an assessor asks for, the common gaps and what to do before publication.

Open the register
6 ANNEXES

Guidance, clearly labelled

Annexes A to F are informative. Each page says so, because a finding cannot rest on guidance alone.

Open the annexes
ONE STAGE RECORD

No invented date

Stage 40.99 is recorded on 16 September 2026. The planning date is an estimate and is labelled wherever it appears.

Read the record

The ISO draft text is not public and is not reproduced. Each record cites the published clause it comes from. Where the public record is silent, the page says so.